Animal Shelter Renovations

Budget:  Included in the $4,500,000 voter approved General Obligation Series 2024 Bond

Funding Source: Series 2024 General Obligation Bond; Public Health Fund Balance

Location: Intersection of Pine and Patterson Streets

  • 4/2/2024 - Bond approved by voters - COMPLETED

  • Fall 2024 - Planning and Design - COMPLETED

  • Spring/Summer 2025 - Finalize design, permitting, and construction packages - COMPLETED

  • Summer 2025 - Construction - IN PROGRESS

  • Spring 2026  - Completion

Timeline

Project Vision

The Animal Shelter Renovation project will create a modern, expanded space for animal shelter operations. The building will be located at the intersection of Pine and Patterson Streets near downtown Pleasant Hill. Planned improvements improve animal enclosures and isolation areas, water access, wash areas, medicine storage, and separate public and staff areas from the enclosures. The improvements will also comply with the Americans with Disabilities Act and improve the exterior visual appearance, creating a clear identity as a shelter.

The original concept included an expanded renovation and operation in the existing building; but the pricing of the renovations coupled with the need for phasing and elevation to meet flood plain requirements would have been more expensive than new construction.

The guaranteed maximum price contract includes a number of designed renderings as construction documents are finalized. The City and the architect may further refine these drawings, but the contract award at minimum will have the following design.

Renderings

Building Layout

The original project concept renovated the existing building on Patterson Street and having the Animal Shelter occupy a majority of the building. During the design phase, the costs of doing so were determined to be more expensive than new construction. Below are the original renderings that were presented to the voters for consideration.

Progress Photos

Current Status

October 2025: exterior CMU wall erection began; slab on grade concrete placed; interior CMU walls began, joist and roof decking; site utilities completed

September 2025: Electrical and plumbing underground rough-in completed; slab on grade concrete placement; CMU block installation; concrete footings completed; door frames set in preparation for block wall erection;

August 2025: Site sub grade completed and passed; footings and foundation begun; site utilities installation began; plumbing rough in started; exterior walls set

July 2025: Contractor mobilized; grading and site work started

June 2025: Groundbreaking ceremony completed

March 2025: Guaranteed Maximum Price contract awarded to Monarch Build

October 2024:

  • 10/28/24 - Preliminary Design build contract awarded to Monarch Build

  • 10/16/24 - Interviews with shortlisted firms

  • 10/8/24; 10/9/24 - Qualification Based responses received and firms shortlisted

September 2024: Requests for Qualifications issued for Design Build Services for Animal Shelter Improvements

August 2024: Navigate Building Solutions selected as Owner’s Representative.

June 2024: Funding has been approved and bonds issued.

April 2024: Prop P2: Puppies and Police Bond approved by voters

Contact Info

Nici Wilson, Interim City Administrator | Email: niciw@pleasanthill.com | Phone: (816) 540-3135

Tommy Wright, Chief of Police | Email: twright@pleasanthill.com | Phone: (816) 540-9109

Conceptual Design: Clark + Enersen

Owner’s Representative: Navigate Building Solutions

Design Build Contractor: Monarch Build