City Lake Updates
Project Vision
Exciting renovations are coming to the City Lake, offering new amenities for everyone to enjoy! The upgrades will focus on the entrance at City Lake with pavement, expanded parking, a restroom/shower facility for comfort and convenience, and a modern playground for kids. These enhancements will transform City Lake into a destination for fun and relaxation!
4/2/2024 - Bond approved by voters
8/13/24 - Preliminary Contract approved COMPLETED
Contract Approval: anticipated 10/28/24 COMPLETED
Phase 1 Completion: July 2025 (originally anticipated Spring 2025) COMPLETED
Phase 2 Completion (if needed): estimated Winter 2025
Timeline
Progress Highlights
Current Status
August 1, 2025: City Lake GRAND OPENING
July 2025: Restroom/shower facility construction completed; way-finding signage installation begun; final walkthroughs started
June 2025: Plumbing and concrete work begun for restroom/shower facility; kayak launch installed; horseshoe drive installed at dump station; parking lot completed
May 2025: Chip and seal main road completed; horse shoe pit concrete slabs poured
April 2025: Grading and site work begun; playground equipment installed
January 2025: Playground equipment has been delivered to 3rd party installer
October 2024:
10/28/24 City Council unanimously approved a construction contract with Precision Construction and Contracting dba PCC Sports for renovations
10/14/24 - Design is over 90% complete
August 2024:
8/12/24 - Council selects PCC Sports as the design build firm and executes a preliminary agreement for design work to be completed over the next 90 days.
8/1/24 - Shortlisted firm interviews completed
July 2024:
7/25/24; 7/26/24 - Qualifications Received and firms shortlisted for interviews
June 2024:
6/26/24 - Request for Qualifications for Design Build Firm
6/21/24 - Navigate Building Solutions selected as Owner’s Representative
6/12/24 - Funding approved and bonds issued
April 2024: Prop P1: Parks Bond approved by voters
Contact Info
Nici Wilson, Interim City Administrator | Email: niciw@pleasanthill.com | (816) 540-3135
Jeff Hull, Director of Parks and Facilities | Email: jhull@pleasanthill.com | (816) 540-3135
Owner’s Representative: Navigate Building Solutions
Design Build Firm: PCC Sports
Design Build Designers: MKEC and Hollis + Miller
Conceptual Design: Clark + Enersen