City Park Renovation
Project Vision
The planned renovations will revitalize the park with fully restored tennis and basketball courts, upgraded parking lots, and enhanced sidewalks. A brand-new children's play area featuring modern playground equipment and a splash pad will provide hours of fun for families. New communal spaces are also being introduced, including pavilions with newly constructed restrooms. Additionally, improved site access will ensure ADA accessibility throughout the park, making it more inclusive and enjoyable for everyone.
4/2/2024 - Bond approved by voters
8/13/24 - Preliminary Agreement approved COMPLETED
Contract Approval: anticipated 10/28/24 COMPLETED
10/30/24 - Groundbreaking COMPLETED
Phase 1 Completion: estimated Spring 2025 COMPLETED
Timeline
Highlights
Current Status
August 1, 2025: City Park GRAND OPENING - additional, minor details (benches, grass growth, landscaping, etc.) to continue over the next few months and be completed by Winter 2025
July 2025: Restroom facility construction completed; sidewalk installation complete; Grand Pavilion and amphitheater construction complete; splash pad cleared for use; grass seed put down; final walkthroughs complete
June 2025: Construction of grand pavilion has begun; playground turf surfacing completed; remaining playground equipment installed; restroom facility construction begun; framing for amphitheater started
May 2025: Grading of amphitheater shelter has begun; excavation for pavilion in progress; turf installation at playgrounds begun additional play equipment installed
April 2025: Sidewalk continuing and stair placement made; base rock complete at playground; splash pad concrete complete; basketball court lines painted; tennis court surfacing nearly complete and all lines installed; rip rap installed at detention pond
March 2025: Playground equipment installed, splash pad plumbing routed
February 2025: Graded and set elevations for playground and splash pad installation; ADA sidewalk poured; parking lot apron installed near tennis court
January 2025: Lighting infrastructure delivered; walking paths framed; Campbell Street sidewalk poured; playground equipment has been delivered to 3rd party installer; water line relocation; Campbell Street parking lot poured
December 2024: Curbing poured for parking lots; parking lot base preparations; tennis court fencing installed
November 2024: Demolition and excavation; Tennis court pad poured; basketball court pad poured
October 2024:
10/28/24 - City Council unanimously approved a construction contract with Precision Construction and Contracting dba PCC Sports for renovations
10/14/24 - Design is over 90% complete
August 2024:
8/12/24 - Council selects PCC Sports as the design build firm and executes a preliminary agreement for design work to be completed over the next 90 days.
8/1/24 - Shortlisted firm interviews completed
July 2024:
7/25/24; 7/26/24 - Qualifications Received and firms shortlisted for interviews
June 2024:
6/26/24 - Request for Qualifications for Design Build Firm
6/21/24 - Navigate Building Solutions selected as Owner’s Representative
6/12/24 - Funding approved and bonds issued
April 2024: Prop P1: Parks Bond approved by voters
Contact Info
Nici Wilson, Interim City Administrator | Email: niciw@pleasanthill.com | (816) 540-3135
Jeff Hull, Director of Parks and Facilities | Email: jhull@pleasanthill.com | (816) 540-3135
Owner’s Representative: Navigate Building Solutions
Design Build Firm: PCC Sports
Design Build Designers: MKEC and Hollis + Miller
Conceptual Design: Clark + Enersen